SUBSTANTIATION FOR MAINTENANCE AND REPAIR SYSTEM FOR PROMISING STRUCTURE OF HIGH-SPEED RAILWAY TRACKS
Abstract and keywords
Abstract (English):
Objective: To create proposals on the system of maintenance for track facilities on the sections with ballastless constructions because the experience in maintaining of such structures is absent. Methods: During the study, the analysis of being predicted life cycle cost of track structure was made. This analysis is based on the study of indicators such as defectiveness of track superstructure elements (rails, fasteners, sleepers), the analysis of being estimated costs on repairing the track using expert evaluation methods. The expert assessment provides for the application of special correction factor. This factor for each maintenance job shows the ratio of job volumes on ballastless track to job volumes on ballast railway track. Results: On the basis of cost calculations and technologies for maintenance, an analysis was pursued of overhaul schemes for sections with ballast railway and for ones with ballastless construction and conclusions were made on required overhaul scheme for a ballastless track structure. Practical importance: The study results are intended to develop a system for planning technical maintenance and repairs of a ballastless superstructure track.

Keywords:
Railway track facilities, railway track, ballastless railway track, railway track maintenance job, overhaul cycle, life cycle cost, railway track maintenance costs
Text
Text (PDF): Read Download
References

1. Feste Fahrbahn Rheda 2000 Rail.One (in German). - April 2011. - Pp. 2f. - Retrieved 17 September 2017.

2. Joaquín J. PonsIgnacio Life cycle assessment of a railway tracks substructures: Comparison of ballast and ballastless rail tracks / Joaquín J. PonsIgnacio, V. Sanchis, V. Yepes // Environmental Impact Assessment Review19 July 2020

3. Kolos A. F. Full - Scale Study of Stress-strain State of Ballastless Upper Structure Construction of Rail Way in Terms of Train Dynamic Load / A. F. Kolos, T. M. Petrova, A. O. Makhonina // Procedia Engineering. - 2017. - Vol. 189. - Pp. 429-433.

4. Robertson I. Advantages of a new ballastless trackform / I. Robertson, C. Masson, J. M. Vanzenberg // Construction and Building: Materials 1 September 2015yu. - Vol. 92. - Pp. 16-22.

5. An accurate method for fast assessment of under slab mats (USM) performance in ballastless track structures.

6. Zbiciak A. Construction and Building / A. Zbiciak, C. Kraśkiewicz, J. Pełczyński // Materials 25 June 2021. - Vol. 300 (Cover date: 20 September 2021). - Article 123953.

7. Firmengruppe M. B. Hochgeschwindigkeit in China mit FF Bögl / M. B. Firmengruppe // MB Quadrat (in German). - 2010. - Pp. 18f.

8. Kruglikov A. Strengthening of the railway ballast section shoulder with two-component polymeric binders / A. Kruglikov, V. Yavna, Z. Khakiev // Transportation Geotechnics. - June 2017. - Vol. 11. - Pp. 133-143.

9. Savin A. V. Vybor konstrukcii puti dlya vysokoskorostnogo dvizheniya / A. V. Savin // Vestnik VNIIZhT. - 2014. - Vyp. 1. - S. 55-59.

10. Garbaruk V. V. Application of Fiber-reinforced Concrete in Tram Track Foundation / V. V. Garbaruk, E. P. Dudkin, V. A. Ivliev // Procedia Engineering. - 2017. - Vol. 189. - Pp. 836-840.

11. Dudkin E. P. Justification and Expansion of Spheres of Application of the Tram / E. P. Dudkin, K. A. Smirnov, S. A. Doronicheva // Procedia Engineering. - Vol. 189. - Pp. 848-853.

12. Dudkin E. P. Methods of Noise and Vibration Protection on Urban Rail Transport / E. P. Dudkin, L. A. Andreeva, N. N. Sultanov // Procedia Engineering. - Vol. 189. - Pp. 829-835.

Login or Create
* Forgot password?